Commercial Operation Date for the newly commissioned capacity is November 4, 2026.
New Delhi, Nov 3 ACME Solar Holdings announced on Tuesday that it has commissioned an additional 66.68 MW of solar power capacity at Bikaner in Rajasthan through its subsidiary, ACME Renewtech Pvt Ltd. With this addition, the total operational capacity of the hybrid project has risen to 200.04 MW.
The Commercial Operation Date (COD) for the newly commissioned capacity is November 4, 2026. Following this commissioning, ACME Solar’s overall operational capacity now stands at around 3,190 MW.
The company said the wind component of the hybrid project will complement its solar generation and help create a more diversified renewable energy profile. The capacity addition further strengthens ACME Solar’s growing portfolio and reflects its focus on building diversified solutions across the renewable energy spectrum.
The hybrid project is located at Kelan Village in Bikaner. Its Power Purchase Agreement (PPA) has been signed with NTPC Ltd at a tariff of Rs 3.36 per kWh. ACME Solar expects to bring the entire 300 MW solar component of the project into operation progressively by the end of Q3 FY27.
ACME Solar Holdings Ltd is a leading integrated renewable energy company with a diversified contracted portfolio of 8,370 MW across solar, wind, energy storage, Firm and Dispatchable Renewable Energy, and hybrid solutions. It has an operational installed capacity of 3,190 MW, along with 5.64 GWh of Battery Energy Storage System (BESS) capacity.